Broadway Construction 2024

Welcome to the Broadway Construction Page!

Project Name:  Broadway Sidewalks (CIP #41606) and Broadway Maintenance (CIP #42003)

Project Limits:  Broadway from Main Street/Mosquito Road to Schnell School Road 

Project Work:  New sidewalks, underground utility work (sewer, storm drain, and water system), and pavement rehabilitation 

Project Contractor:  Doug Veerkamp General Engineering, Inc.

Project Start Date:  March 18, 2024

Project End Date:   End of December 2024  (**Weather delays in November extended the project end date**)

Project Contacts:  Melissa McConnell, City of Placerville Engineering Department - (530) 642-5250, mmcconnell@cityofplacerville.org

                                Dion Carr, Resident Engineer, Dewberry Engineers, dcarr@dewberry.com, (916) 276-4721 


Project Updates:

December 16, 2024:    Weekly Update 37

December 9, 2024:   Weekly Update 36

November 1, 2024:    Weekly Update 32  November 9, 2024:    Weekly Update 33  November 18, 2024:   Weekly Update 34  November 25, 2024:   Weekly Update 35

October 7, 2024:    Weekly Update 28   October 12, 2024:    Weekly Update 29  October 19, 2024:    Weekly Update 30  October 25, 2024:   Weekly Update 31 

September 2, 2024:   Weekly Update 23   September 9, 2024:    Weekly Update 24   September 14, 2024:    Weekly Update 25   September 20, 2024:     Weekly Update 26   September 30, 2024:    Weekly Update 27

August 2, 2024:   Weekly Update 19    August 9, 2024:     Weekly Update 20   August 17, 2024:    Weekly Update 21   August 24, 2024:      Weekly Update 22

July 1, 2024:     Weekly Update 14    July 8, 2024:    Weekly Update 15   July 15, 2024:   Weekly Update 16   July 22, 2024:   Weekly Update 17   July 29, 2024:    Weekly Update 18 

June 3, 2024:    Weekly Update 10   Broadway Night Work Exhibit    June 10, 2024:    Weekly Update 11    June 17, 2024:    Weekly Update 12   June 24, 2024:    Weekly Update 13

May 3, 2024:    Weekly Update 6    May 10, 2024:   Weekly Update 7   May 17, 2024:   Weekly Update 8   May 28, 2024:    Weekly Update 9 

April 9, 2024:    Weekly Update 3  April 19, 2024:   Weekly Update 4   April 26, 2024:   Weekly Update 5

March 29, 2024:  Project construction began on Wednesday, March 20th!  During the first few weeks, the contractor is potholing to confirm utilities. In the second week of April, the contractor will begin the underground utility work starting at Mosquito Road. Please pay close attention to traffic control as the work location moves during potholing, and reduce speeds in the work zones. Thank you! 

March 4, 2024: Utility companies (PG&E, AT&T, and Comcast) will be performing utility relocation work prior to the City's contractor starting work. Please pay close attention to traffic control and reduce speeds in the work zones. Thank you!