Welcome to the Placerville Drive Pedestrian Connectivity Project (CIP 42337)
Project Limits: On Placerville Drive from Fair Lane (at the US 50 Interchange) to Armory Drive
Project Work: Sidewalk will be constructed on the west side of the street from US 50 to the fairgrounds entrance, and on the east side of the street from the fairground entrance to Armory Drive. The project includes improvements to the fairgrounds crosswalk, minor storm drain improvements, pavement rehabilitation, and roadway striping.
Project Contractor: Doug Veerkamp General Engineering, Inc.
Dion Carr, Resident Engineer, Dewberry Engineers, dcarr@dewberry.com, (916) 276-4721
Start Construction: September 19, 2025
End Construction: January 2026
01-16-25 Meeting Exhibit of Project Improvements
The City held the second open-house style public meeting on January 16, 2025.
The City held an open-house style public meeting for the project on August 23, 2023.